Richardson Road over South Prong St. Mary River Replacement
Overview

The existing Richardson Road bridge over South Prong St. Mary River is a single-lane, seven-span structure. The bridge is 87.5-ft long, 12-ft wide, and composed of concrete slabs supported by timber columns. Constructed in 1960, the bridge connects two unpaved segments of Richardson Road.

This PD&E study proposes to replace the existing bridge with a single-lane, cast-in-place concrete slab bridge supported by concrete columns. The proposed bridge will be built wide enough to be used as a two-lane bridge after the future widening of Richardson Road into a two-lane road.

Project Photos
No photos at this time.
Project Documents
No documents at this time.
Hybrid Public Hearing (In-Person) (Thursday, November 14, 2024)

The Florida Department of Transportation (FDOT) District 2 invites you to the Hybrid Public meeting for the Richardson Road over South Prong St. Mary River Project Development & Environment (PD&E) Study. FDOT is conducting a PD&E Study to replace the Richardson Road bridge (No. 274114) over a tributary of the St. Mary River. The purpose of this meeting is to inform the public of the evaluated alternatives and provide an opportunity for the public to express their opinions and concerns regarding the project.

For your convenience, there are several options to participate in the public meeting including an in-person option, a virtual / online option, and a dial in option. All participants, regardless of the platform they choose, will receive the same information on the proposed project, and all comments received in-person, virtually, or electronically, will be given equal weight.

Open House: 4:30 pm to 6:30 pm
Public Comment Period: 6:30 pm
Location:
Community Full Gospel Church
12664 Mud Lake Road
Glen St. Mary, Florida 32040

After reviewing the meeting materials, and / or participating, you may submit comments in several ways:

  • During the virtual meeting or in-person meeting
  • Email the FDOT Project Manager Jared Sweat, at Jared.Sweat@dot.state.fl.us
  • Mail comments to FDOT District 2 Office at 1109 S. Marion Avenue, Lake City, Florida 32025

While comments about the project are accepted at any time, please note that comments must be received by November 22, 2024 to be included in the formal meeting record.

Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability, or family status. People who require special accommodations under the Americans with Disabilities Act or who require translation services (free of charge) should contact Jared Sweat, Project Manager, at the information provided below at least seven (7) days prior to the meeting.

The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried out by Florida Department of Transportation (FDOT) pursuant to 23 U.S.C. §327 and a Memorandum of Understanding dated May 26, 2022 and executed by the Federal Highway Administration and FDOT.

Project Details
Project Start:TBD
Expected Completion:TBD
Cost:TBD
Project #:436333-1
Roads
CountiesBaker
CitiesGlen St. Mary
Contact
Photo of Jared SweatJared Sweat
386-961-7462
Richardson Road over South Prong St. Mary River Replacement
Overview

The existing Richardson Road bridge over South Prong St. Mary River is a single-lane, seven-span structure. The bridge is 87.5-ft long, 12-ft wide, and composed of concrete slabs supported by timber columns. Constructed in 1960, the bridge connects two unpaved segments of Richardson Road.

This PD&E study proposes to replace the existing bridge with a single-lane, cast-in-place concrete slab bridge supported by concrete columns. The proposed bridge will be built wide enough to be used as a two-lane bridge after the future widening of Richardson Road into a two-lane road.

Project Details
Project Start:TBD
Expected Completion:TBD
Cost:TBD
Project #:436333-1
Roads
CountiesBaker
CitiesGlen St. Mary
Contact
Photo of Jared SweatJared Sweat
386-961-7462
Events
Hybrid Public Hearing (In-Person) (Thursday, November 14, 2024)

The Florida Department of Transportation (FDOT) District 2 invites you to the Hybrid Public meeting for the Richardson Road over South Prong St. Mary River Project Development & Environment (PD&E) Study. FDOT is conducting a PD&E Study to replace the Richardson Road bridge (No. 274114) over a tributary of the St. Mary River. The purpose of this meeting is to inform the public of the evaluated alternatives and provide an opportunity for the public to express their opinions and concerns regarding the project.

For your convenience, there are several options to participate in the public meeting including an in-person option, a virtual / online option, and a dial in option. All participants, regardless of the platform they choose, will receive the same information on the proposed project, and all comments received in-person, virtually, or electronically, will be given equal weight.

Open House: 4:30 pm to 6:30 pm
Public Comment Period: 6:30 pm
Location:
Community Full Gospel Church
12664 Mud Lake Road
Glen St. Mary, Florida 32040

After reviewing the meeting materials, and / or participating, you may submit comments in several ways:

  • During the virtual meeting or in-person meeting
  • Email the FDOT Project Manager Jared Sweat, at Jared.Sweat@dot.state.fl.us
  • Mail comments to FDOT District 2 Office at 1109 S. Marion Avenue, Lake City, Florida 32025

While comments about the project are accepted at any time, please note that comments must be received by November 22, 2024 to be included in the formal meeting record.

Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability, or family status. People who require special accommodations under the Americans with Disabilities Act or who require translation services (free of charge) should contact Jared Sweat, Project Manager, at the information provided below at least seven (7) days prior to the meeting.

The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried out by Florida Department of Transportation (FDOT) pursuant to 23 U.S.C. §327 and a Memorandum of Understanding dated May 26, 2022 and executed by the Federal Highway Administration and FDOT.

 
Link to FDOT's Facebook page (opens new browser window) Link to FDOT's Twitter page (opens new browser window) Link to FDOT's YouTube page (opens new browser window) Link to FDOT's Wordpress page (opens new browser window) Link to FDOT's Multimedia page (opens new browser window) Link to FDOT's RSS page (opens new browser window)