I-95 from S.R. 207 to International Golf Parkway resurfacing
Overview

The Florida Department of Transportation began a twelve mile resurfacing project on I-95 from State Road 207 to International Golf Parkway in early October 2021. During the project, crews will mill and resurface the existing three-lane northbound and southbound roadway of I-95 from State Road 207 to International Golf Parkway, including the interstate entry and exit ramps at State Road 207 and State Road 16.

Improvements will also include construction of a Median U-Turn Intersection along State Road 16 at the I-95 Interchange. This new interchange concept has been widely utilized in other parts of the United States, however it will be the first full Median U-Turn intersection constructed in the State of Florida. Drivers approaching a Median U-Turn intersection who desire to turn left will be routed straight through the intersection and diverted to a one way median opening located several hundred feet from the main intersection. This configuration will eliminate left-turning movements from the main intersection and reduced signal cycle times, which will result in increased safety and overall shorter travel times.

Other improvements will include 6-laning of State Road 16 through the interchange, milling and resurfacing and pier protection along State Road 207, and upgrades to signalization, roadway lighting and the Intelligence Transportation Systems (ITS) throughout the project limits. Temporary lane closures will be permitted on Sunday through Thursday nights from 8 p.m. to 6 a.m.

Anderson Columbia was selected to complete both improvement projects.

Traffic Impacts
Project Photos
I-95 207 to IGD resurfacing projectJune 2023- progress aerial photosJune 2023- progress aerial photos
Project Documents
Project diagram overview
Construction Open House (Wednesday, September 29, 2021)

The Florida Department of Transportation (FDOT) will be hosting a hybrid construction open house: Wednesday, September 29 2021, online at nflroads.com/VPH or by phone at (415) 655-0060 Access code 613-141-732 Citizens who are unable to participate virtually or by phone may attend the hearing in person at: St Johns County Auditorium, 500 San Sebastian View, St Augustine, Florida 32084 from 4 to 6 p.m. The public commenting period will begin at 6 p.m. In-person attendance will be limited to adhere to St. Johns County social distancing requirements. Citizens are encouraged to participate virtually. Both virtual and in-person participants will be given equal opportunity to ask questions and make oral statements that will become part of the public hearing record.

GoToWebinar (IE not supported):
https://attendee.gotowebinar.com/register/4889774916385748751
Webinar ID:961-194-843

Project Details
Project Start:October 2021
Expected Completion:Early 2025
Cost:$20 million
Project #:434615-1
RoadsInterstate 95
CountiesSt. Johns
CitiesSt. Augustine
Contact
Photo of Jacob PickeringJacob Pickering
904-360-5471
I-95 from S.R. 207 to International Golf Parkway resurfacing
Overview

The Florida Department of Transportation began a twelve mile resurfacing project on I-95 from State Road 207 to International Golf Parkway in early October 2021. During the project, crews will mill and resurface the existing three-lane northbound and southbound roadway of I-95 from State Road 207 to International Golf Parkway, including the interstate entry and exit ramps at State Road 207 and State Road 16.

Improvements will also include construction of a Median U-Turn Intersection along State Road 16 at the I-95 Interchange. This new interchange concept has been widely utilized in other parts of the United States, however it will be the first full Median U-Turn intersection constructed in the State of Florida. Drivers approaching a Median U-Turn intersection who desire to turn left will be routed straight through the intersection and diverted to a one way median opening located several hundred feet from the main intersection. This configuration will eliminate left-turning movements from the main intersection and reduced signal cycle times, which will result in increased safety and overall shorter travel times.

Other improvements will include 6-laning of State Road 16 through the interchange, milling and resurfacing and pier protection along State Road 207, and upgrades to signalization, roadway lighting and the Intelligence Transportation Systems (ITS) throughout the project limits. Temporary lane closures will be permitted on Sunday through Thursday nights from 8 p.m. to 6 a.m.

Anderson Columbia was selected to complete both improvement projects.

Project Details
Project Start:October 2021
Expected Completion:Early 2025
Cost:$20 million
Project #:434615-1
RoadsInterstate 95
CountiesSt. Johns
CitiesSt. Augustine
Contact
Photo of Jacob PickeringJacob Pickering
904-360-5471
Events
Construction Open House (Wednesday, September 29, 2021)

The Florida Department of Transportation (FDOT) will be hosting a hybrid construction open house: Wednesday, September 29 2021, online at nflroads.com/VPH or by phone at (415) 655-0060 Access code 613-141-732 Citizens who are unable to participate virtually or by phone may attend the hearing in person at: St Johns County Auditorium, 500 San Sebastian View, St Augustine, Florida 32084 from 4 to 6 p.m. The public commenting period will begin at 6 p.m. In-person attendance will be limited to adhere to St. Johns County social distancing requirements. Citizens are encouraged to participate virtually. Both virtual and in-person participants will be given equal opportunity to ask questions and make oral statements that will become part of the public hearing record.

GoToWebinar (IE not supported):
https://attendee.gotowebinar.com/register/4889774916385748751
Webinar ID:961-194-843

Project Documents
Project diagram overview
Project Photos
I-95 207 to IGD resurfacing projectJune 2023- progress aerial photosJune 2023- progress aerial photos
 
Link to FDOT's Facebook page (opens new browser window) Link to FDOT's Twitter page (opens new browser window) Link to FDOT's YouTube page (opens new browser window) Link to FDOT's Wordpress page (opens new browser window) Link to FDOT's Multimedia page (opens new browser window) Link to FDOT's RSS page (opens new browser window)

Florida Department of Transportation

Consistent, Predictable, Repeatable