U.S. 17 from North Boundary Road to State Road 207 Resurfacing
Overview

Halifax Paving, Inc. was selected to complete this $8.3 million project, which includes milling and resurfacing of the roadway, corridor improvements, base work, shoulder treatment, drainage improvements, curb and gutter work, lighting improvements, highway signing, guardrail installation, sidewalk work, pavement markings and other incidental construction.

Traffic will be maintained in accordance with FDOT design standards throughout the project. Motorists should expect lane closures from 8:30 a.m.to 5:30 p.m. Monday through Friday. No lane closures will be permitted from 6 a.m. to 8:30 a.m. Monday through Friday.

Traffic Impacts
U.S. 17 traffic impacts
February 10-16, 2024
Daytime lane closures from north of North Boundary Road to north of Yelvington Road weekdays from 8:30 a.m. to 6:30 p.m. and daytime lane closures Saturday from 7:30 a.m. to 6:30 p.m. for drainage work.
Project Photos
December 2023- Progress photosDecember 2023- Progress photosDecember 2023- Progress photosDecember 2023- Progress photosDecember 2023- Progress photosDecember 2023- Progress photosDecember 2023- Progress photos
Project Documents
No documents at this time.
No Events at this time.
Project Details
Project Start:October 2023
Expected Completion:Winter 2024
Cost:$8.27 million
Project #:439115-1
RoadsU.S. 17
CountiesPutnam
CitiesPalatka
Contact
Photo of Brie IsomBrie Isom
904-360-5457
U.S. 17 from North Boundary Road to State Road 207 Resurfacing
Overview

Halifax Paving, Inc. was selected to complete this $8.3 million project, which includes milling and resurfacing of the roadway, corridor improvements, base work, shoulder treatment, drainage improvements, curb and gutter work, lighting improvements, highway signing, guardrail installation, sidewalk work, pavement markings and other incidental construction.

Traffic will be maintained in accordance with FDOT design standards throughout the project. Motorists should expect lane closures from 8:30 a.m.to 5:30 p.m. Monday through Friday. No lane closures will be permitted from 6 a.m. to 8:30 a.m. Monday through Friday.

Project Details
Project Start:October 2023
Expected Completion:Winter 2024
Cost:$8.27 million
Project #:439115-1
RoadsU.S. 17
CountiesPutnam
CitiesPalatka
Contact
Photo of Brie IsomBrie Isom
904-360-5457
Traffic Impacts
U.S. 17 traffic impacts
February 10-16, 2024
Daytime lane closures from north of North Boundary Road to north of Yelvington Road weekdays from 8:30 a.m. to 6:30 p.m. and daytime lane closures Saturday from 7:30 a.m. to 6:30 p.m. for drainage work.
Project Photos
December 2023- Progress photosDecember 2023- Progress photosDecember 2023- Progress photosDecember 2023- Progress photosDecember 2023- Progress photosDecember 2023- Progress photosDecember 2023- Progress photos
 
Link to FDOT's Facebook page (opens new browser window) Link to FDOT's Twitter page (opens new browser window) Link to FDOT's YouTube page (opens new browser window) Link to FDOT's Wordpress page (opens new browser window) Link to FDOT's Multimedia page (opens new browser window) Link to FDOT's RSS page (opens new browser window)