State Road 207 Resurfacing from I-95 to State Road 312
Overview
The FDOT is scheduled to begin work on milling and resurfacing of State Road 207 between I-95 and State Road 312 in St. Augustine. Halifax Paving, Inc. was selected to complete the improvement project which includes milling and resurfacing of the roadway, shoulder treatment, new highway signage, traffic signals, sidewalks and bicycle path. Other repairs of the roadway and incidental construction items are included in this contract to bring State Road 207 up to current standards. Detours and lane closures on State Road 207 will be limited during the project, with none permitted from 6 a.m. to 9 p.m. Monday through Sunday.
Traffic Impacts
State Road 207 traffic impacts
February 10-16, 2024
Nighttime lane closures from Marketplace Drive to Osceola Elementary Road weeknights from 9 p.m. to 6 a.m. for paving.
Project Photos
297 Map
Project Documents
No documents at this time.
No Events at this time.
Project Details
Project Start:Early 2023
Expected Completion:Winter 2024
Cost:$8 million
Project #:445546-1-52-01 & 445546-1-52-02
RoadsState Road 207
CountiesSt. Johns
CitiesSt. Augustine
Contact
Photo of Jacob PickeringJacob Pickering
904-360-5471
State Road 207 Resurfacing from I-95 to State Road 312
Overview
The FDOT is scheduled to begin work on milling and resurfacing of State Road 207 between I-95 and State Road 312 in St. Augustine. Halifax Paving, Inc. was selected to complete the improvement project which includes milling and resurfacing of the roadway, shoulder treatment, new highway signage, traffic signals, sidewalks and bicycle path. Other repairs of the roadway and incidental construction items are included in this contract to bring State Road 207 up to current standards. Detours and lane closures on State Road 207 will be limited during the project, with none permitted from 6 a.m. to 9 p.m. Monday through Sunday.
Project Details
Project Start:Early 2023
Expected Completion:Winter 2024
Cost:$8 million
Project #:445546-1-52-01 & 445546-1-52-02
RoadsState Road 207
CountiesSt. Johns
CitiesSt. Augustine
Contact
Photo of Jacob PickeringJacob Pickering
904-360-5471
Traffic Impacts
State Road 207 traffic impacts
February 10-16, 2024
Nighttime lane closures from Marketplace Drive to Osceola Elementary Road weeknights from 9 p.m. to 6 a.m. for paving.
Project Photos
297 Map
 
Link to FDOT's Facebook page (opens new browser window) Link to FDOT's Twitter page (opens new browser window) Link to FDOT's YouTube page (opens new browser window) Link to FDOT's Wordpress page (opens new browser window) Link to FDOT's Multimedia page (opens new browser window) Link to FDOT's RSS page (opens new browser window)