SR 200 (SR A1A) from Griffin Road to I-95 Resurfacing
Overview

FDOT started a resurfacing project on State Road 200 (State Road A1A) from Griffin Road to I-95 in September 2022. Improvements under this contract consist of milling and resurfacing, base work, shoulder treatment,highway signing, and other incidental construction on 5.067 miles of State Road 200 in Nassau County. Atlantic Coast Asphalt was selected to complete this project.

Traffic Impacts
State Road A1A traffic impacts
November 26-December 2, 2022
Daytime westbound lane closures at Semper Fi Drive Monday through Saturday from 2 a.m. to 10 p.m. for road work.
State Road A1A traffic impacts
November 26-December 2, 2022
Eastbound lane closures from Midway Road to Amelia Road weekdays and weeknights from 9 a.m. to 4 a.m. for concrete work.
Project Photos
No photos at this time.
Project Documents
No documents at this time.
No Events at this time.
Project Details
Project Start:September 2022
Expected Completion:Fall 2023
Cost:$13.19 million
Project #:445341-1-52-01
RoadsState Road 200, State Road A1A
CountiesNassau
CitiesYulee
Contact
Photo of Samantha RambeauSamantha Rambeau
904-360-5484
SR 200 (SR A1A) from Griffin Road to I-95 Resurfacing
Overview

FDOT started a resurfacing project on State Road 200 (State Road A1A) from Griffin Road to I-95 in September 2022. Improvements under this contract consist of milling and resurfacing, base work, shoulder treatment,highway signing, and other incidental construction on 5.067 miles of State Road 200 in Nassau County. Atlantic Coast Asphalt was selected to complete this project.

Project Details
Project Start:September 2022
Expected Completion:Fall 2023
Cost:$13.19 million
Project #:445341-1-52-01
RoadsState Road 200, State Road A1A
CountiesNassau
CitiesYulee
Contact
Photo of Samantha RambeauSamantha Rambeau
904-360-5484
Traffic Impacts
State Road A1A traffic impacts
November 26-December 2, 2022
Daytime westbound lane closures at Semper Fi Drive Monday through Saturday from 2 a.m. to 10 p.m. for road work.
State Road A1A traffic impacts
November 26-December 2, 2022
Eastbound lane closures from Midway Road to Amelia Road weekdays and weeknights from 9 a.m. to 4 a.m. for concrete work.
 
Link to FDOT's Facebook page (opens new browser window) Link to FDOT's Twitter page (opens new browser window) Link to FDOT's YouTube page (opens new browser window) Link to FDOT's Wordpress page (opens new browser window) Link to FDOT's Multimedia page (opens new browser window) Link to FDOT's RSS page (opens new browser window)