State Road 26 Resurfacing from east of U.S. 301 to State Road 21
Overview

Milling and resurfacing on State Road 26 from east of State Road 200 (U.S. 301) to State Road 21 began Monday, Jan. 6, 2025.

The project includes milling and resurfacing, base work, drainage improvements, curb and gutter, sidewalks, signalization, signing and pavement markings, and other incidental construction.

V.E. Whitehurst & Sons, Inc. was awarded the $5.9 million project.

Traffic will be maintained in accordance with Florida Department of Transportation design standards throughout the project. Work is expected to occur daily from 7 a.m. to 5:30 p.m. Monday through Friday and 6:30 p.m. to 6:30 a.m. Sunday through Thursday.

Traffic Impacts
Project Photos
No photos at this time.
Project Documents
No documents at this time.
No Events at this time.
Project Details
Project Start:January 2025
Expected Completion:August 2025
Cost:$5.9 million
Project #:207823-3
RoadsState Road 26
CountiesPutnam
CitiesMelrose
Contact
Photo of Emily HarringtonEmily Harrington
904-519-6990 x213
State Road 26 Resurfacing from east of U.S. 301 to State Road 21
Overview

Milling and resurfacing on State Road 26 from east of State Road 200 (U.S. 301) to State Road 21 began Monday, Jan. 6, 2025.

The project includes milling and resurfacing, base work, drainage improvements, curb and gutter, sidewalks, signalization, signing and pavement markings, and other incidental construction.

V.E. Whitehurst & Sons, Inc. was awarded the $5.9 million project.

Traffic will be maintained in accordance with Florida Department of Transportation design standards throughout the project. Work is expected to occur daily from 7 a.m. to 5:30 p.m. Monday through Friday and 6:30 p.m. to 6:30 a.m. Sunday through Thursday.

Project Details
Project Start:January 2025
Expected Completion:August 2025
Cost:$5.9 million
Project #:207823-3
RoadsState Road 26
CountiesPutnam
CitiesMelrose
Contact
Photo of Emily HarringtonEmily Harrington
904-519-6990 x213
 
Link to FDOT's Facebook page (opens new browser window) Link to FDOT's Twitter page (opens new browser window) Link to FDOT's YouTube page (opens new browser window) Link to FDOT's Wordpress page (opens new browser window) Link to FDOT's Multimedia page (opens new browser window) Link to FDOT's RSS page (opens new browser window)